Fuselage Kit Order
  [December 26, 2006]: Ordered Fuselage
  [December 27, 2006]: Confirmed order
  [January 5, 2007]: Received fuselage order confirmation
  [March 1, 2007]: Fuselage shipped
  [March 12, 2007]: Fuselage Arrived

Fuselage Inventory [8.5 Hours]
  [April 1, 2007]: [0.5 Hours] Started Inventory
  [April 2, 2007]: [3.5 Hours] More Inventory
  [April 3, 2007]: [3 Hours] Even More Inventory
  [April 4, 2007]: [1.5 Hours] Finished Inventory

Firewall [11.25 Hours]
  [April 7, 2007]: [0.25 Hours] Found firewall parts
  [April 9, 2007]: [0.25 Hours] Started fabricating F-601J angle
  [April 10, 2007]: [1 Hour] Finished fabricating F-601J angle.
  [April 11, 2007]: [1 Hour] Misc firewall prep stuff
  [April 12, 2007]: [1 Hour] More firewall drilling
  [April 13, 2007]: [3 Hours] Prepped firewall parts
  [April 14, 2007]: [1 Hour] Primed firewall parts
  [April 15, 2007]: [0.5 Hours] Deburred Firewall
  [April 16, 2007]: [3 Hours] Started riveting firewall
  [April 17, 2007]: [0.25 Hours] Finished Firewall

Bulkheads [40.5 Hours]
  [April 7, 2007]: [1 Hour] Fluted bulkheads
  [April 17, 2007]: [2.5 Hours] Started center section, aka F-704 bulkhead
  [April 18, 2007]: [2.5 Hours] More center section work
  [April 19, 2007]: [2 Hours] Finished F-704 bulkhead prep, started F-705 bulkhead
  [April 20, 2007]: [4 Hours] More work on the F-705 bulkhead
  [April 21, 2007]: [3 Hours] F-705 seatback parts
  [April 22, 2007]: [2 Hours] More f-705 work
  [April 23, 2007]: [2.5 Hours] Finished F-705 prep, started F-706 bulkhead
  [April 24, 2007]: [2 Hours] Finished F-706, 707 and 708 bulkheads
  [April 25, 2007]: [2 Hours] Finished F-709, 710 bullheads, started F-711
  [April 26, 2007]: [0.5 Hours] Finished bulkhead prep
  [April 27, 2007]: [5 Hours] Started deburring bulkhead parts
  [April 28, 2007]: [2 Hours] Finished deburring bulkheads
  [April 29, 2007]: [3.5 Hours] primed bulkheads
  [April 30, 2007]: [0.25 Hours] Started riveting bulkheads
  [May 1, 2007]: Ordered autopilot pitch servo bracket
  [May 2, 2007]: [2.5 Hours] Interior Color R&D, bulkhead riveting
  [May 4, 2007]: [0.25 Hours] Riveted F-712 bulkhead
  [May 5, 2007]: [3 Hours] Finished riveting bulkheads

Longerons [13.5 Hours]
  [May 7, 2007]: [2.5 Hours] Cut longerons
  [May 9, 2007]: [2 Hours] Started bending longeron
  [May 10, 2007]: [2 Hours] More longeron bending
  [May 11, 2007]: [2.5 Hours] Finished long shallow bend, drilled aft canopy deck, started downward bend
  [May 12, 2007]: [3 Hours] Finished bending longerons, cut j-stiffeners
  [May 13, 2007]: [1.5 Hours] Finished j-stiffener cuts

Aft Fuselage [31.75 Hours]
  [May 14, 2007]: [3 Hours] Started aft fuselage
  [May 15, 2007]: [2.5 Hours] Started clecoing aft fuselage.
  [May 16, 2007]: [3 Hours] Finished clecoing aft fuselage
  [May 18, 2007]: [0.25 Hours] Leveled out aft fuselage
  [May 21, 2007]: [2.5 Hours] Backdrilled j-stiffeners
  [May 22, 2007]: [0.5 Hours] More match drilling
  [May 23, 2007]: [1 Hour] Finished drilling aft fuselage
  [May 30, 2007]: [2 Hours] Final drilled tailwheel bracket; Pitch servo installation
  [May 31, 2007]: [1.5 Hours] Edge deburring
  [June 1, 2007]: [3 Hours] Finished deburring
  [June 2, 2007]: [8 Hours] Primed, dimpled and reassembled aft fuse
  [June 14, 2007]: [4.5 Hours] Riveted aft fuselage

Center Fuselage [52.25 Hours]
  [June 4, 2007]: [0.5 Hours] Fabricated F-916C spacers
  [June 5, 2007]: [3 Hours] F-715/716 rib work
  [June 6, 2007]: [2.5 Hours] Clecoed together center fuselage
  [June 7, 2007]: [0.5 Hours] Finished drilling bottom skin, started F-623 side rib
  [June 8, 2007]: [4 Hours] More center section work
  [June 12, 2007]: [2 Hours] Crotch strap bracket
  [June 15, 2007]: [2 Hours] Center section prep.
  [June 16, 2007]: [2 Hours] Wrapped up center section prep
  [June 18, 2007]: [2.5 Hours] Started deburring
  [June 19, 2007]: [2 Hours] Finished deburring
  [June 21, 2007]: [1 Hour] Prepped parts for priming
  [June 22, 2007]: [3.5 Hours] Primed center section
  [June 24, 2007]: [5 Hours] Riveted center section skeleton
  [June 25, 2007]: [1 Hour] Clecoed skin back on
  [June 26, 2007]: [3 Hours] Started riveting center section skin.
  [June 27, 2007]: [2.5 Hours] Finished riveting center section
  [June 28, 2007]: [1.5 Hours] drilled floors, F-715 rib
  [June 29, 2007]: [4 Hours] Joined center section to aft fuselage
  [June 30, 2007]: [6 Hours] Side Skins
  [July 1, 2007]: [1 Hour] Worked on longeron fit on aft fuselage
  [July 3, 2007]: [0.75 Hours] Started drilling longeron to aft fuselage
  [July 4, 2007]: [2 Hours] More longeron drilling

Forward Fuselage [49.5 Hours]
  [July 5, 2007]: [4 Hours] Finished drilling longerons, mounted firewall
  [July 6, 2007]: [10 Hours] Drilled firewall, aux longeron, stiffeners, fabbed lower longerons
  [July 7, 2007]: [2 Hours] Futzed around with the lower longerons
  [July 8, 2007]: [0.5 Hours] Fabricated F-684 corner brace
  [July 9, 2007]: Lower Longeron answer fron Vans
  [July 11, 2007]: [2 Hours] Drilled right lower longeron to engine bracket, attached corner brace
  [July 12, 2007]: [1 Hour] Finished right corner brace, Gear attach web fitting
  [July 13, 2007]: [2 Hours] Drilled gear attach web, started tank attach hardware fabrication
  [July 14, 2007]: [0.5 Hours] Fabricated F-796B angle
  [July 16, 2007]: [2 Hours] Drilled tank attach interior brackets, started brakes
  [July 17, 2007]: [1 Hour] Assembled brake pedals
  [July 18, 2007]: [2 Hours] Assembled and mounted brake pedals
  [July 19, 2007]: [3 Hours] Finished mounting brake pedals, got parts
  [July 20, 2007]: [1.5 Hours] Misc forward firewall work.
  [July 25, 2007]: [3 Hours] remade left lower longeron
  [July 26, 2007]: [1 Hour] Left gear attach web
  [July 27, 2007]: [7 Hours] Attached rudder pedals; installed floor stiffeners
  [July 30, 2007]: [1.5 Hours] Finished floor stiffeners, installed baggage ribs
  [August 2, 2007]: [2.5 Hours] Fixing F-724 fit against F-623
  [August 3, 2007]: [3 Hours] Last work on fuselage before disassembly

Forward Fuse Prep [51.5 Hours]
  [August 4, 2007]: [1 Hour] Disassembled fuselage
  [August 6, 2007]: [1 Hour] Took center section off
  [August 7, 2007]: [2 Hours] Deburred side skins
  [August 8, 2007]: [2.5 Hours] Deburred parts
  [August 9, 2007]: [1 Hour] More deburring
  [August 10, 2007]: [4 Hours] Finished deburring
  [August 11, 2007]: [1.5 Hours] Started countersinking longeron
  [August 13, 2007]: [2 Hours] Countersinking Mania!
  [August 16, 2007]: [4 Hours] More prep work
  [August 17, 2007]: [4 Hours] Reinforced armrests, priming prep
  [August 18, 2007]: [8 Hours] Primed fuse parts; played with JetFlex
  [August 19, 2007]: [2 Hours] Side skin deburring
  [August 20, 2007]: [2.5 Hours] Deburring and dimpling
  [August 21, 2007]: [1.5 Hours] Dimpling
  [August 22, 2007]: [1 Hour] Misc prep work
  [August 23, 2007]: [1 Hour] Paint Prep
  [August 28, 2007]: [2 Hours] Started painting interior
  [August 30, 2007]: [2.5 Hours] More interior painting
  [September 4, 2007]: [3 Hours] More Painting
  [September 5, 2007]: [2.5 Hours] Firewall Sealant/More Painting
  [September 6, 2007]: [2.5 Hours] FINISHED INTERIOR PAINTING!!!

Forward Fuse Assembly [21 Hours]
  [September 9, 2007]: [6 Hours] Started fuse assembly
  [September 10, 2007]: [2.5 Hours] Made fuse stand
  [September 11, 2007]: [2.5 Hours] Started riveting
  [September 12, 2007]: [3.5 Hours] Riveted aft of F-704 bulkhead
  [September 13, 2007]: [2 Hours] Sealed firewall to side/bottom skins
  [September 14, 2007]: [2.5 Hours] Riveted forward of the F-704 bulkhead
  [September 18, 2007]: [0.5 Hours] Misc assembly
  [October 9, 2007]: [1.5 Hours] Flipped the canoe!

Aft Deck and Top Skins [24.5 Hours]
  [October 11, 2007]: [3 Hours] Drilled aft deck
  [October 13, 2007]: [4 Hours] Gussets and Braces
  [October 14, 2007]: [3 Hours] Front brace
  [October 15, 2007]: [3 Hours] Seat belt anchor, riveted F-728, deburred
  [October 16, 2007]: [4 Hours] Primed parts, riveted aft deck & elevator bellcrank
  [October 22, 2007]: [3 Hours] Fit elevator bellcrank, started top skin.
  [October 23, 2007]: [3.5 Hours] Finished top skins
  [October 25, 2007]: [1 Hour] Riveted aft bulkhead gusset plates

Fuselage Cabin Area [85.5 Hours]
  [October 25, 2007]: [2.5 Hours] Drilled forward canopy deck; work in baggage area
  [October 26, 2007]: [2.5 Hours] Rear baggage bulkhead skin
  [October 27, 2007]: [3 Hours] Installed nutplates for rear baggage skin
  [October 28, 2007]: [1.5 Hours] Made seatbelt wear blocks
  [October 29, 2007]: [2.5 Hours] Cut holes in baggage floor
  [October 30, 2007]: [1.5 Hours] Drilled holes for conduit under baggage floors
  [November 1, 2007]: [2 Hours] Made conduit brackets
  [November 2, 2007]: [3.5 Hours] Finished baggage floor conduit; prepped parts
  [November 3, 2007]: [2 Hours] Primed and painted parts
  [November 4, 2007]: [1 Hour] Installed side panels
  [November 5, 2007]: [4 Hours] Installed baggage floors
  [November 6, 2007]: [3.5 Hours] Aft seat floors
  [November 7, 2007]: [2.5 Hours] Started seat backs
  [November 8, 2007]: [3 Hours] More seatback work
  [November 9, 2007]: [3 Hours] Finished seatback fabrication; started tunnel cover
  [November 10, 2007]: [3 Hours] Finished tunnel cover; started forward covers
  [November 12, 2007]: [4 Hours] Forward Covers
  [November 13, 2007]: [3.5 Hours] Finished cover fabrication; started flap system
  [November 14, 2007]: [3 Hours] Work on flap system
  [November 15, 2007]: [2 Hours] Finished flap system
  [November 16, 2007]: [2 Hours] Prep work
  [November 17, 2007]: [1 Hour] Quick Deburring
  [November 19, 2007]: [3 Hours] More deburring
  [November 20, 2007]: [4 Hours] Even more parts prep
  [November 24, 2007]: [3 Hours] Final prep before paint
  [November 25, 2007]: [4 Hours] Painted parts
  [November 27, 2007]: [3 Hours] Misc assembly; Prepping top aft skins
  [November 28, 2007]: [2.5 Hours] Misc Stuff
  [November 29, 2007]: [2 Hours] Made stick boot rings
  [December 2, 2007]: [3 Hours] Pushrods
  [December 4, 2007]: [2 Hours] Finished flap pushrods
  [December 18, 2007]: [2.5 Hours] Finished seat backs

Canopy Frame [27 Hours]
  [December 5, 2007]: [2 Hours] Drilled static ports, started Canopy Frame
  [December 7, 2007]: [2.5 Hours] Canopy frame prep
  [December 8, 2007]: [8 Hours] Drilled canopy frame
  [December 12, 2007]: [5 Hours] Prepped and primed
  [December 13, 2007]: [1 Hour] Assembled frame
  [December 15, 2007]: [3.5 Hours] Attached frame to fuse
  [December 16, 2007]: [3.5 Hours] Finished up canopy frame fabrication
  [December 17, 2007]: [1.5 Hours] Made cover for channel

Front Deck [26.5 Hours]
  [December 19, 2007]: [2 Hours] Worked on angles
  [December 20, 2007]: [2.5 Hours] Fit angle to the back of panel
  [December 26, 2007]: [1.5 Hours] Worked on subpanel parts
  [January 25, 2008]: [1.5 Hours] Fit hat section on center subpanel
  [January 26, 2008]: [4 Hours] Attached subpanel to fuselage
  [January 28, 2008]: [2 Hours] Finished up subpanel drilling..onto deburring
  [January 29, 2008]: [3.5 Hours] Deburred subpanel parts
  [January 30, 2008]: [3 Hours] Dimpled and started assembly
  [February 16, 2009]: [4 Hours] Painted subpanel
  [February 17, 2009]: [2.5 Hours] Riveted subpanel

Wing Mating [51 Hours]
  [February 26, 2008]: [3 Hours] Started prep for wing mating
  [February 28, 2008]: [1 Hour] More wing mating prep
  [March 1, 2008]: [4 Hours] Mated the wings!
  [March 2, 2008]: [3 Hours] Trimmed rear spar fork
  [March 3, 2008]: [4.5 Hours] Drilled rear spar to fuselage.
  [March 4, 2008]: [3.5 Hours] Attached forward tank bracket; mounted control surfaces.
  [March 5, 2008]: [3 Hours] Left flap work
  [March 6, 2008]: [2 Hours] Finished setting flaps.
  [March 8, 2008]: [5 Hours] Rigged ailerons; wing root farings.
  [March 9, 2008]: [3.5 Hours] Interior vent lines run
  [March 10, 2008]: [4 Hours] Finished tubing; worked on misc wing issues
  [March 11, 2008]: [3.5 Hours] Aileron stops; Started aileron trim system
  [March 12, 2008]: [1 Hour] Aileron trim
  [March 13, 2008]: [2 Hours] Finished aileron trim
  [March 15, 2008]: [8 Hours] Un-mated wings; misc wing/fuse work

Tail Surface Mounting [22 Hours]
  [March 17, 2008]: [2 Hours] Elevator work
  [March 18, 2008]: [2 Hours] Drilled elevator hinge
  [March 19, 2008]: [4 Hours] Mounted horizontal stabilizer, started vertical stabilizer mounting
  [March 20, 2008]: [3 Hours] Set vertical stabilizer
  [March 21, 2008]: [5 Hours] Finished mounting vertical stabilizer and rudder
  [March 22, 2008]: [6 Hours] Fixed right elevator - finished tail mounting

Misc Fuselage [29.5 Hours]
  [May 24, 2008]: [10 Hours] Tons of little tasks
  [May 27, 2008]: [2 Hours] Attached NACA ducts; made aft fuselage conduit supports
  [June 4, 2008]: [4 Hours] Riveted aft top skins
  [June 10, 2008]: [2.5 Hours] Riveted F-705 bulkhead and canopy decks
  [June 11, 2008]: [2 Hours] Installed F-704 covers, prepped fuse for paint
  [June 12, 2008]: [3 Hours] Painted fuselage
  [June 17, 2008]: [3 Hours] Painted Rudder weldment, misc stuff
  [June 23, 2008]: [1.5 Hours] Rudder Fairings
  [June 24, 2008]: [1.5 Hours] Finished rudder fairings